Facilities
Facilities Manager
Robert Spirito
Maintenance Manager
Ken Laroche
Maintenance Technicians
Ed Goodwin
James Cochran
The district's facilities management team developed the Facility Maintenance Plan to document the way the Derry Cooperative School District will maintain its buildings and grounds to ensure a safe and sanitary condition for its students and staff, and to protect the district's investment in its assets through sound maintenance procedures.
The district contracted with Lavallee Brensinger Architects to conduct a thorough assessment of the conditions of all nine of the district-owned buildings. This included a Facilities Assessment, an evaluation of the current conditions of the nine facilities, and a Long-Range Facility Plan, using the facilities assessment to identify both short-term and long-term actions to address all facility shortcomings, educational visioning for the future, and prioritizing items from the most pressing to those that can be addressed in future years.
The Derry Cooperative School District contracted with Jobin Construction Consultants to conduct a study on the cost of capital improvement projects to solve the top issues at each school. These projects would improve the facilities without educational visioning upgrades and without bringing the buildings back to like-new condition.
The district contracted with Gale Associates to perform evaluations of the building envelopes at Derry Village, South Range and West Running Brook. These evaluations focused on issues that were identified by the Lavallee Brensinger building assessments.
- Facade Report-WRB (07/23/24)
- Evaluation of Derry Village School (06/05/23)
- Evaluation of South Range School (06/05/23)
- Presentation on DVS & SRS Evaluations (06/06/23)
- Evaluation of West Running Brook School (06/15/23)
- Presentation on WRB Evaluation (6/20/23)
- Proposal for Repairs to WRB Facade (09/27/23)
- 75% Design Submission for Repairs to WRB Facade (01/30/24)
- spallSTOP Spec (03/26/24)
The district entered into an agreement with Honeywell in order to provide more efficiency to the heating, cooling, and overall air handling efforts of the district. Their services have saved the district millions of dollars in energy costs and their recommendations are valued for providing the most efficient resources for the district.
- Derry Cooperative School District Administrative Facilities Presentation& presented again on 2/14/2023
- Derry Cooperative School District Administrative Facilities Presentation 1/31/2023
- Parent Comments/Questions to the School Board regarding 1/31 Administrative Facilities Presentation
- Facilities Master Plan Updates (Updated June 7, 2022)
- Facilities Committee Presentation - May 24, 2022
- DCSD School Board Update - May 10th, 2022
- DCSD Design Meeting #2 - May 10th, 2022
- DCSD Design Meeting #1 - April 25th, 2022
- DCSD School Board presentation - Community Forum - April 7th, 2022
- DCSD School Board Workshop presentation - March 24th, 2022
Derry Village Elementary School
- Parent Letters: April 9, 2019, June 5, 2019
- Results: April 5, 2019, May 7, 2019, May 22, 2019
East Derry Memorial Elementary School
- Parent Letters: April 11, 2019, June 5, 2019
- Results: April 9, 2019, May 7, 2019, May 22, 2019
Ernest P. Barka Elementary School
- Parent Letters: April 16, 2019
- Results: April 15, 2019
Gilbert H. Hood Middle School
- Parent Letters: April 9, 2019, June 5, 2019
- Results: April 5, 2019, May 7, 2019
Grinnell Elementary School
- Parent Letters: April 15, 2019
- Results: April 12, 2019
South Range Elementary School
- Parent Letters: April 15, 2019
- Results: April 12, 2019
West Running Brook Middle School
- Parent Letters: April 8, 2019, June 5, 2019
- Results: April 3, 2019, May 7, 2019, May 23, 2019
Derry Village Elementary School
- Parent Letter: June 16, 2023
- Results: June 8, 2023
East Derry Memorial Elementary School
- Parent Letter: June 28, 2023
- Results: June 21, 2023
Ernest P. Barka Elementary School
- Parent Letter: July 6, 2023
- Results: July 5, 2023
Gilbert H. Hood Middle School
- Parent Letter and Test Results: August 15, 2023
Grinnell Elementary School
- Parent Letter: June 28, 2023
- Results: June 21, 2023
South Range Elementary School
- Parent Letter: June 28, 2023
- Results: June 21, 2023
West Running Brook Middle School
- Parent Letter: June 16, 2023
- Results: June 14, 2023
Derry Village Elementary School
- Parent Letter: March 28, 2024
- Resuts: March 26, 2024
East Derry Memorial Elementary School
- Parent Letter: April 8, 2024
- Results: April 2, 2024
Ernest P. Barka Elementary School
- Parent Letter: March 28, 2024
- Results: March 26, 2024
Gilbert H. Hood Middle School
- Parent Letter: May 29, 2024
- Results: May 24, 2024
Grinnell Elementary School
- Results: April 9, 2024
South Range Elementary School
- Parent Letter: March 28, 2024
- Results: March 26, 2024
West Running Brook Middle School
- Parent Letter: May 15, 2024
- Assessment of Educational Facility Needs K-8 Public Forum (11/24/14)
- Facilities Study Committee Final Report and Recommendations Phase Two (6/1/2016)
- Facilities Study Committee Phase III Final Report and recommendations (9/1/2017)
- Facilities Study Committee Phase III Final Report Appendices (9/1/2017)
- Facilities Study Committee Phase III Final Report and Recommendations Presentation (10/10/2017)
- 5 Year Maintenance Improvement Plan (12/3/2018)
- Facilities Committee Presentation (5/24/2022)
- Facilities Maintenance Plan (6/1/2022)
- Facilities Master Planning Workshop (8/30/2022)
- Facilities Master Planning Workshop (10/20/2022)
- Top Issue Repair Projects Derry Village (12/1/2022)
- Top Issue Repair Projects East Derry (12/1/2022)
- Top Issue Repair Projects Ernest P. Barka (12/1/2022)
- Top Issue Repair Projects Grinnell (12/1/2022)
- Top Issue Repair Projects South Range (12/1/2022)
- Top Issue Repair Projects Gilbert H. Hood (12/1/2022)
- Top Issue Repair Projects West Running Brook (12/1/2022)
- Other Archived Documents
East Derry Memorial Elementary School: East Derry Memorial School was constructed in 1986. The 58,000 square foot facility sits on 20 acres of land. Recent upgrades include:
- Nearly all HVAC equipment and both boilers were replaced during the Honeywell project.
- In late 2021 the building was converted from well water to public water. ($160,000)
- Carpet is being replaced with VCT on an ongoing basis in classrooms as needed. (average $20,000/yr)
- The fire alarm system is original to the building and should be replaced with a modern, addressable platform. ($250,000 - In progress, summer 2024)
Ernest P. Barka Elementary School: Ernest P. Barka Elementary School was constructed in 2004. The 90,000 square foot facility sits on 17 acres of land. Recent upgrades include:
- Domestic water booster pumps were replaced with modern units. ($30,000)
- Carpet is being replaced with VCT in classrooms as needed. (average $20,000/yr)
- The roofing system is compromised and requires immediate replacement. ($840,000 - In progress, Summer 2024)
Gilbert H. Hood Middle School: Gilbert H. Hood Middle School was constructed in three phases. The initial phase was completed in 1950. Major renovations and additions were completed in the early 1970s and the earlly 2000s. The nearly 170,000 square foot facility sits on 22 acres of land. This building also houses the Derry Early Education Program (DEEP) as well as Next Charter School. Recent upgrades include:
- Both boilers were replaced during the Honeywell project.
- A sidewalk was added to the bus lane along the southwest side of the building. ($80,000)
- Carpet is being replaced with VCT in classrooms as needed. (average $20,000/yr)
Grinnell Elementary School: Grinnell Elementary School was constructed in three phases. The initial phase was completed in 1950. Additions were made to the building in 1986 and 2008. The 70,000 square foot facility sits on 6 acres of land. Recent upgrades include:
- Both boilers were replaced during the Honeywell project.
- The building received a new water main. ($160,000)
- Carpet is being replaced with VCT in classrooms as needed. (average $20,000/yr)
- The main entrance was reconstructed. ($30,000)
- Windows and seams were sealed. ($10,000)
South Range Elemenary School: South Range Elementary School was constructed in 1966. The 51,000 square foot facility sits on roughly 12 acres of land. An addition was constructed in 2000 which added instructional space as well as a dedicated gymnasium. Recent upgrades include:
- The parking lot was recently repaved.
- Carpet is being replaced with VCT in classrooms as needed. (average $20,000/yr)
West Running Brook Intermediate School: West Running Brook was constructed in 1994. The 110,000 square foot facility sits on 40 acres of land. Recent upgrades include:
- The parking lot pavement was recently replaced.
- Interior and exterior door replacements have been ongoing.
- Carpet is being replaced as needed. (average $20,000/yr)
- The roof needs to be replaced. ($725,000 - In progress, summer 2024)
- The dry sprinkler system causes consistent issues and needs to be replaced with modern technology. ($160,000 - In progress, summer 2024)